East Coast Main Line: Timetables

(asked on 15th December 2022) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, in what (a) month and (b) year his Department planned to deliver the East Coast Main Line timetable change when funding was announced in July 2018 for the East Coast Upgrade engineering works.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 20th December 2022

In July 2018 the ECML timetable change related to the ECML Upgrade was to be delivered in December 2020.