Question to the Department for Transport:
To ask the Secretary of State for Transport, a) how many full or partial weekend closures affecting London Liverpool Street services have occurred since July 2024; b) what assessment she has made of the economic impact of weekend engineering works on commuters and businesses in eastern England; and c) what steps her Department is taking to improve network resilience during major engineering works.
It is very rare to close Liverpool Street on a weekend for longer than 27 hours and not on a Saturday. Network Rail will occasionally consider closing the full station on a Sunday as, with train operators, they can offer alternative travel options into London for passengers. However, there have been some full weekend closures of Liverpool Street station because of extensive eight-day engineering blocks undertaken over Christmas 2024 and 2025 to carry out major roof renovations at the station. Note that on these occasions, services terminated at Stratford, with connections into the Liverpool Street area available.
Network Rail analyses routes across the whole of the UK to minimise disruption to critical passenger and freight flows such as those to London Gateway and Felixstowe reducing the impact to a minimum as practically as possible.
Network Rail plans major engineering works to coincide with expected low overall passenger demand (for example, by not planning works on popular seaside routes in mid-Summer). Network Rail aims to maintain operational resilience, to minimise disruption, and to ensure the safe and efficient delivery of major engineering works, and timely completion of those works.