Railways: Dawlish

(asked on 13th October 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how much it cost to reconstruct the railway at Dawlish; and from which budget that cost was met.


Answered by
 Portrait
Claire Perry
This question was answered on 21st October 2015

£35m was spent repairing the most damaged section of the track and sea wall and associated works during the initial 56-day work period at Dawlish. Work to raise the walkway is additional and has an anticipated final cost of £15.3m. Funding came in two phases: Phase 1 emergency work was funded primarily from insurance with the Network Rail structures renewals budget paying the excess of £2m. Phase 2 (raising the walkway) will be funded through Network Rail’s Control Period 5 (2019-24) structure renewals budget.