Question to the Ministry of Housing, Communities and Local Government:
To ask the Secretary of State for Housing, Communities and Local Government, how many cladding remediation applications submitted to the Building Safety Regulator have exceeded the 12-week service level agreement for determination since November 2025.
The Building Safety Regulator (BSR) has increased their regulatory capacity throughout 2025. There were 115 posts approved, with 83 members of staff already onboarded.
The BSR’s monthly Building Control Approval data was released on 25th February 2026 for data between December 2025 and February 2026. The median wait time between submission and approval of Gateway 2 applications for cladding remediation works on Higher-Risk Buildings which include some older applications was 31 weeks.
Newer applications (received in 2026) are currently being determined significantly quicker due to both improving quality of applications as well as more efficient BSR processes. The BSR is currently launching a plan that will further drive down application times and help unsafe buildings be remediated at pace.
In relation to remediation applications, the statutory target for issuing a determination is eight weeks.
The BSR confirms that, of the 117 Gateway 2 remediation applications received since November 2025, the current position is as follows:
Status | Number | Timeframe |
Invalidated | 7 | Determined within the 8-week SLA |
Rejected | 5 | Determined after more than 12 weeks |
Withdrawn | 1 | Withdrawn after more than 12 weeks |
Live Case | 45 | Still within the 8-week SLA |
Live Case | 26 | Exceeding 8 weeks but under 12 weeks |
Live Case | 30 | Exceeding 12 weeks |