Network Rail: Staff

(asked on 1st December 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what proportion of Network Rail's expenditure in each year of (a) Control Period 4 and (b) the current Control Period 5 to date was on (i) in-house and (ii) third-party or contingent labour.


Answered by
Paul Maynard Portrait
Paul Maynard
This question was answered on 6th December 2017

% in house

% external

CP4

09/10

27

73

10/11

27

73

11/12

24

76

12/13

24

76

13/14

20

80

CP5

14/15

21

79

15/16

21

79

16/17

22

78

The main reason for the increase in the proportion of external costs over this period is the record level of investment in enhancement projects which have greater involvement from third party contractors.