Network Rail: Cost Effectiveness

(asked on 1st December 2017) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, if he will list the total value of efficiency savings achieved by Network Rail over (a) Control Period 3, (b) Control Period 4 and (c) Control Period 5 to date; and what proportion of that saving was from (i) direct labour costs, (ii) capital expenditure and (iii) debt servicing.


Answered by
Paul Maynard Portrait
Paul Maynard
This question was answered on 6th December 2017


Opex – index

Efficiency (17/18 prices £m)

03/04

100.0

CP3

04/05

87.0

537

05/06

79.0

867

06/07

75.5

1,012

07/08

71.5

1,177

08/09

70.0

1,239

CP4

09/10

70.4

1,220

10/11

64.2

1,479

11/12

59.5

1,671

12/13

58.9

1,695

13/14

60.3

1,640

CP5

14/15

57.0

1,775

15/16

57.0

1,774

16/17

55.5

1,836


Opex savings of 45% have been achieved over the past 13 years using the regulator’s measure of efficiency as set out in the table above. This equates to total savings of nearly £18bn in current prices.

Data records are not available to show how much of the efficiency saving made has been due to direct labour costs. Capital expenditure, meanwhile, is not measurable in a comparable way – the value of expenditure can vary significantly each year depending upon the projects being undertaken.

In addition, debt servicing is not included when assessing efficiency savings. Network Rail’s interest expense is driven by external factors which are outside their control.

Reticulating Splines