Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the answer of 18 March 2026 to Question 120007, whether any elements of the HS2 programme’s scope, specification or associated works are expected to change in order to align the programme with the Spending Review settlement for FY2025-26 to FY2029-30.
The Spending Review settlement profiles reflects the scope, specification and associated works that the HS2 programme plans to deliver over the period. The HS2 programme reset work that Mark Wild is currently undertaking is underpinned by the Spending Review settlement.