School Rebuilding Programme

(asked on 17th January 2023) - View Source

Question to the Department for Education:

To ask the Secretary of State for Education, what her planned timetable is for starting work on schools that have been selected for the School Rebuilding Programme; and if she will make a statement.


Answered by
Nick Gibb Portrait
Nick Gibb
This question was answered on 23rd January 2023

161 of the 400 projects selected for the School Rebuilding Programme are in delivery. Buildings at the most advanced projects will be completed early this year. The schools announced in December 2022 will enter delivery at a rate of approximately 50 per year, over a five-year period from 2023.

The Department is currently undertaking due diligence on these schools. The Department will be writing to all Responsible Bodies with an update on timescales this month.