M6: Repairs and Maintenance

(asked on 10th April 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the total duration in hours was of (a) partial and (b) full closures as a result of the M6 Lune Gorge project.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 20th April 2026

Between 1 September 2025 and 14 April 2026, all recorded closures associated with preparatory works were partial closures only, affecting a single northbound or southbound carriageway, or lane closures. There were 18 overnight carriageway closures, each operating within a standard nine hour window (8pm – 5am), giving up to 162 hours of partial closures. In addition, lane closures from January 2026 total up to 270 hours. There were no full closures affecting both directions simultaneously during this period.