Railways: North West

(asked on 8th February 2018) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the timetable is for a decision to be made on the funding for the Hope Valley Line improvement scheme.


This question was answered on 22nd February 2018

On 13 February 2018, the Secretary of State announced his decision to provide Network Rail Infrastructure Limited with the legal powers to construct, operate and maintain new passing facilities and associated railway infrastructure on the Hope Valley route between Bamford and Hathersage and at Dore. Network Rail have completed the single option design for the railway infrastructure scheme proposed in the Hope Valley and, following last week’s decision, the timetable for further work on this scheme including a final investment decision will be announced in due course.