Langstone Harbour: Water Treatment

(asked on 22nd April 2026) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, whether she has made an assessment of the environmental risks associated with constructing the proposed effluent recycling plant on a contaminated landfill site adjacent to Langstone Harbour SSSI.


Answered by
Emma Hardy Portrait
Emma Hardy
Parliamentary Under-Secretary (Department for Environment, Food and Rural Affairs)
This question was answered on 27th April 2026

The Environment Agency has, through its role in the Nationally Significant Infrastructure planning process, assessed potential risks of constructing the proposed water recycling plant on a former landfill.

The Environment Agency considers these risks to be manageable with appropriate design and mitigation.