Chinook Helicopters: Procurement

(asked on 5th February 2024) - View Source

Question to the Ministry of Defence:

To ask the Secretary of State for Defence, what his timetable is for taking a final decision on the procurement of Chinook H-47 extended-range helicopters.


Answered by
James Cartlidge Portrait
James Cartlidge
Minister of State (Ministry of Defence)
This question was answered on 15th February 2024

The Review Note for the Chinook extended range helicopter programme is due to be assessed by the Ministry of Defence Investment Approvals Committee in Quarter 1 2024 and will inform any future decisions affecting the current programme of record.

As the assessed costs and schedule for the programme are currently under consideration it would be inappropriate to disclose the figures and programme timelines until a full review has taken place.