Energy: Business

(asked on 22nd April 2026) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what assessment he has made of the potential impact of the time taken for grid connection on the ability of businesses to lower energy costs through onsite generation.


Answered by
Michael Shanks Portrait
Michael Shanks
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 27th April 2026

Following Ofgem’s decision to increase the threshold for generation requiring a transmission impact assessment from 1MW to 5MW in England and Wales[1], it is now quicker and cheaper for businesses customers to install onsite generation. Ofgem’s Connections End‑to‑End Review will also improve customer service and reduce connection times for such projects[2].

1 https://www.ofgem.gov.uk/sites/default/files/2025-05/CMP446%20-%20Authority%20decision%20to%20approve%20WACM%201.pdf

2 https://www.ofgem.gov.uk/consultation/connections-end-end-review-updated-proposals-and-next-steps