Nuclear Reactors

(asked on 23rd April 2018) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, whether the Design Acceptance Certificate for the European Pressurised Reactor (EPR) could be used for a re-designed EPR; and if he will make a statement.


This question was answered on 1st May 2018

A Design Acceptance Confirmation (DAC) completes the Generic Design Assessment (GDA) led by the UK’s independent regulators to assess non-site specific (i.e. generic) aspects of new reactor designs. GDA is not a statutory requirement of the nuclear licensing regime and any site specific elements of EPR design will be assessed by the Office for Nuclear Regulation as part of a site specific safety case ahead of any construction.