Lakeside Energy from Waste

(asked on 14th June 2018) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether his Department has made an assessment of how long the relocation of Lakeside Energy from Waste will take in the event of a third runway being constructed at Heathrow Airport.


Answered by
Jesse Norman Portrait
Jesse Norman
Shadow Leader of the House of Commons
This question was answered on 21st June 2018

The Government has not undertaken a separate assessment of how long it would take to relocate the plant because relocation is not necessary from a statutory or policy perspective. However if relocation was to take place, the Airports Commission estimated that the process may take five years.