Question to the HM Treasury:
To ask the Chancellor of the Exchequer, with reference to the contract HMT OSCAR II Procurement, published by his Department on 24 April 2019, how much his Department has paid to Deloitte LLP under the terms of the contract as of 22 April 2022; and how much public expenditure has been allocated for further payments under the terms of the contract in (a) the rest of 2022-23 and (b) 2023-24.
£9.734m has been paid to Deloitte LLP under the terms of the OSCAR II contract as of 19th April 2022. (The question was received, and the system interrogated on 20 April 2022. Data is only final following the close of each day, so it was necessary to use 19 April 2022)
For 22-23 there is a £1.2m budget for project milestones and £1.6m budget for the managed service costs.
For 23-24 there is a £302k budget for project milestones and £774k for the managed service costs (this is less than 22-23 because this contract ends in November 2023).