High Rise Flats: Insulation

(asked on 28th February 2024) - View Source

Question to the Department for Levelling Up, Housing & Communities:

To ask the Secretary of State for Levelling Up, Housing and Communities, what information he holds on the number and proportion of buildings over 18 meters with aluminium composite material cladding that have started remediation works.


Answered by
Lee Rowley Portrait
Lee Rowley
Minister of State (Minister for Housing)
This question was answered on 5th March 2024

The latest data on remediation progress of high-rise buildings (over 18 metres) with aluminium composite material (ACM) cladding systems unlikely to meet Building Regulations is available at: https://www.gov.uk/government/publications/building-safety-remediation-monthly-data-release-january-2024.

Reticulating Splines