Question to the Department for Transport:
To ask the Secretary of State for Transport, when he expects the A1M motorway northbound carriageway to be resurfaced; and what plans he has to remove potholes between junctions 1 and 2 of that motorway.
There is a programme of resurfacing on the A1(M) as follows:
A1(M) J1 – J6
A1(M) J1-J2 – Minor repairs were completed mid-April, with further enhanced inspections beginning week commencing 24 April 2023. Larger scale resurfacing will be undertaken dependent on inspection outcome.
A1(M) J14-J17
NH have plans to undertake some resurfacing of the A1M northbound between J15 to J16 lane 1. Works are expected to be completed around August/September 2023
A1(M) J8 – J10
National Highways has plans to carry out minor surface repairs before the end of April. No plans for larger-scale resurfacing until the next roads investment period, 2025-2030.
A1(M) J52 – J53
Reprofiling Scheme starting 05/06/2023
A1(M) J60 – J61
Climbing Lanes patching scheme work starting 18/09/2023
A1(M) J61 – J62
Hard Shoulder patching scheme work starting 30/10/2023
This carriageway is inspected on a weekly basis and 10 potholes were repaired overnight on 18 and 19 April 2023 at J1 – J2. National Highways will be conducting enhanced inspections during the week commencing 24 April 2023.