Housing: Solar Power

(asked on 23rd May 2023) - View Source

Question to the Department for Energy Security & Net Zero:

To ask the Secretary of State for Energy Security and Net Zero, what the average time was to issue a smart export guarantee certificate under the microgeneration certification scheme to households that have newly-installed solar panels in the latest period for which data is available.


Answered by
Graham Stuart Portrait
Graham Stuart
Minister of State (Department for Energy Security and Net Zero)
This question was answered on 1st June 2023

For consumer protection purposes, households are required to demonstrate that their solar panels and installer are suitably certified to receive payment under the Smart Export Guarantee. Certificates issued under the independent Microgeneration Certification Scheme should be issued by installers within 10 days of the system being commissioned.

The Department does not hold data on the average time taken to issue an MCS certificate.