Fracking: Lancashire

(asked on 5th November 2018) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, what assessment his Department has made of the adequacy of the waste water disposal system at the Preston New Road Shale Gas site.


Answered by
Thérèse Coffey Portrait
Thérèse Coffey
This question was answered on 12th November 2018

Environmental permits issued by the Environment Agency set legally binding conditions. The permit at Preston New Road allows for hydraulic fracturing fluid that returns to the surface, known as flowback fluid, to be reused and recycled onsite in the process. Flowback fluid that cannot be recycled will become waste, and must be taken offsite for treatment at appropriately licensed waste water treatment facilities.

Waste flowback is not expected to be produced at the site until further into the fracturing programme. At that time the Environment Agency plan to carry out a full audit of flowback storage, sampling and disposal.

Reticulating Splines