Question to the Department for Transport:
To ask the Secretary of State for Transport, when he plans to make a decision on the Windmill Junction East Croydon grade-separated capacity enhancement.
The proposed works at Windmill Bridge Junction and East Croydon form part of a wider Brighton Mainline (BML) upgrade programme, led by Network Rail.
An Outline Business Case (OBC) is expected to be complete in late 2019. Consistent with our new Rail Enhancements Pipeline process, once the OBC is finalised, a decision will be made whether to progress and fund the Final Business Case (FBC) stage and further development of the project, leading ultimately to a final investment decision over the coming years. Our decision to deliver the programme will be based on there being a sound business case, planning permission, and overall affordability.