High Speed 2 Line

(asked on 1st September 2023) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, whether the Final Land Acquisition Boundary process for HS2 has been completed; and when he plans to publish those documents.


Answered by
Huw Merriman Portrait
Huw Merriman
Minister of State (Department for Transport)
This question was answered on 7th September 2023

The Final Land Acquisition Boundary (FLAB) process is a fixed process undertaken over several months to determine and assure each individual land requirement in advance of a notice being served. It is a collaborative process between all key stakeholders including construction partners to review the Land Request requirements, review progress of actions against any known complex issues, and ensure compliance with Undertakings & Assurances and mitigation of risks.

It is an iterative process and will be ongoing as the HS2 programme progresses.