Schools: Buildings

(asked on 4th September 2023) - View Source

Question to the Department for Education:

To ask the Secretary of State for Education, what estimate she has made how many schools in addition to those already identified are affected by reinforced autoclaved aerated concrete (RAAC).


Answered by
David Johnston Portrait
David Johnston
Parliamentary Under-Secretary (Department for Education)
This question was answered on 18th September 2023

This Government has taken more proactive action on RAAC than any other in the UK. Nothing is more important than the safety of children and staff. It has always been the case that where we are made aware of a building that may pose an immediate risk, the Department takes immediate action. It is the responsibility of those who run schools – academy trusts, Local Authorities, and voluntary aided school bodies – who work with their schools on a day to day basis, to manage the safety and maintenance of their schools and to alert us if there is a concern with a building.

The Department is providing responsible bodies with a range of support to identify RAAC within their estates and ensure that the associated risks are mitigated.

The Department has issued repeated guidance since 2018 to all responsible bodies highlighting the potential risks associated with RAAC and supporting them to identify this within their buildings, as well as to take appropriate steps in meeting their obligations to keep buildings safe. Our most recent guidance is available at: https://www.gov.uk/government/publications/reinforced-autoclaved-aerated-concrete-estates-guidance.

There are over 22,000 schools and colleges in England, and the vast majority are unaffected. A significant proportion of the estate was built outside the period where RAAC was used, with around one third of the estate being built since 2001, therefore, the Department has focused efforts on buildings built in the post-war decades.

The Department issued a questionnaire in March 2022, asking responsible bodies to inform the Department of any suspected RAAC identified in their estates. Responsible bodies have submitted questionnaires for over 98% of schools with blocks built in the target era, of which there are 14,900. The Department is pressing all remaining schools to get checks completed, to determine which schools require surveys.

The Department has also published updated guidance to support settings where the presence of RAAC is confirmed. All schools where RAAC is confirmed are provided with a dedicated caseworker to support them and help implement a mitigation plan and minimise the disruption to children’s learning. This guidance is available at: https://www.gov.uk/government/publications/reinforced-autoclaved-aerated-concrete-guidance-for-responsible-bodies-and-education-settings-with-confirmed-raac.

Departments have been asked to report on the current picture of suspected and confirmed RAAC in their estates as soon as possible. The Government published lists of education settings confirmed as having RAAC on Wednesday 6 September and committed to providing further updates. The published list is available at: https://www.gov.uk/government/publications/reinforced-autoclaved-aerated-concrete-raac-management-information.

On the question of timescales, our focus is on supporting schools and colleges to put in place suitable mitigations to minimise disruption to learning. The Department will fund emergency mitigation work needed to make buildings safe, including installing alternative classroom space where necessary. The Department will also fund longer term refurbishment projects, or rebuilding projects where these are needed, to rectify the RAAC issue in the long term. Where schools and colleges need additional help with revenue costs, like transport to locations or temporarily renting a local hall or office, the Department will provide that support for all reasonable requests. Longer-term refurbishment projects, or rebuilding projects will also be funded where these are needed, to rectify the RAAC issue in the long term.

All previously confirmed School Rebuilding Programme projects announced in 2021 and 2022 will continue to go ahead. A full list of confirmed projects can be found here: https://www.gov.uk/government/publications/school-rebuilding-programme-schools-in-the-programme.