Afghanistan

(asked on 4th June 2014) - View Source

Question to the Department for International Development:

To ask the Secretary of State for International Development, what official agreements were made between her Department and the Afghan Investment Support Agency for any work relating to the (a) Bost Agri Industrial Park and (b) Bost Airfield.


Answered by
Justine Greening Portrait
Justine Greening
This question was answered on 11th June 2014

The Bost industrial business park proposal was originally approved by officials in 2009 at a time when Ministers did not approve spend under £40m. In 2012 it became clear that the project could no longer be completed within the original timeframe and in good order. To avoid wasting taxpayers' money I decided that UK funding for the project should be cancelled. The completed park designs have been handed over to the Afghan authorities to enable them to pursue the project over a revised time frame. DFID's work on Bost Airfield was completed in November 2013.

DFID put a Memorandum of Understanding in place with AISA and the Helmand Provincial Government in April 2012, focusing solely on the development of the Bost Agri Business Park. AISA was not engaged on the Bost Airfield.

Reticulating Splines