Wind Power: Electrical Substations

(asked on 4th June 2014) - View Source

Question

To ask the Secretary of State for Energy and Climate Change, if he will take steps to ensure that onshore windfarm developers take into account the costs of (a) overground cables and (b) underground cables between a windfarm and its sub-station when taking decisions on laying such cables.


Answered by
Michael Fallon Portrait
Michael Fallon
This question was answered on 11th June 2014

Onshore windfarm developers already take into account the costs of different connection options as part of their commercial decisions. In addition, developers submitting applications for nationally significant infrastructure proposals are required to consider alternative options for connections, including undergrounding and routes, as part of the planning consent process.