Railways: Electrification

(asked on 15th December 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what costs his Department has incurred as a result of delays to the TransPennine Midland Main Line, and Great Western Main Line electrification project.


Answered by
 Portrait
Claire Perry
This question was answered on 18th December 2015

The department has not incurred any additional costs as a result of Sir Peter Hendy’s re-plan of the rail upgrade programme, which includes TransPennine, Midland Main Line, and Great Western Main Line electrification.