Mobile Phones

(asked on 10th October 2014) - View Source

Question to the Department for Digital, Culture, Media & Sport:

To ask the Secretary of State for Culture, Media and Sport, how much of the budget for the Mobile Infrastructure Project has been spent to date; how many sites have been built under that project; and what the completion date for the project is.


Answered by
Lord Vaizey of Didcot Portrait
Lord Vaizey of Didcot
This question was answered on 15th October 2014

The Mobile Infrastructure Project currently has 135 sites in acquisition stage, with options for site locations under investigation. There are 15 sites where planning applications have been submitted, 2 sites are being built, and to date 2 sites have gone live in Weaverthorpe, North Yorkshire, and North Molton in Devon, providing coverage to over 200 premises each. The project has so far spent £3.87 million.

The Government is committed to taking mobile coverage to as many premises as possible. Therefore the project will continue beyond March 2015 to ensure as many communities as possible benefit.

Reticulating Splines