Question
To ask the Secretary of State for Energy and Climate Change, how many onshore wind turbine applications in Nottinghamshire were (a) approved and (b) rejected in (i) 2012, (ii) 2013 and (iii) 2014 to date.
The Renewable Energy Planning Database (REPD) tracks the progress of projects through the planning system:
https://www.gov.uk/government/collections/renewable-energy-planning-data
The September 2014 version of the REPD shows the planning applications for onshore wind installations in Nottinghamshire, which have been approved and refused, as follows:
2012 | 2013 | 2014 to date | |
Approved | 1 | 4 | 1 |
Refused | 2 | 4 | 4 |
Note: The dates for approval and refusal reflects the date of determination of appeal (where appeal decision reached), otherwise the date of determination of original application.