Fracking: Earthquakes

(asked on 25th February 2019) - View Source

Question to the Department for Business, Energy and Industrial Strategy:

To ask the Secretary of State for Business, Energy and Industrial Strategy, what assessment he has made of the adequacy of regulations governing earthquakes as a result of fracking.


Answered by
 Portrait
Claire Perry
This question was answered on 5th March 2019

The Traffic Light System for monitoring induced seismicity was introduced after consideration of advice from three scientists, following operations at Cuadrilla’s Preese Hall site in 2011. The level of magnitude 0.5 at which operators must pause operations, was set in consultation with industry as an appropriate precautionary measure. These regulations have been working as intended and there are no plans to review the traffic light system.