Question to the Ministry of Defence:
To ask the Secretary of State for Defence, with reference to the Ministry of Defence annual report and accounts 2025 to 2026, Losses, if he will provide further information on the £6,321,000 constructive loss in relation to the Quinquennial Review Property write-offs.
The £6,321,000 constructive loss relates to property assets identified as derelict or demolished during the Quinquennial Review (QQR) asset revaluation. The Valuation Office Agency and DIO Overseas Estates team conduct this review annually on one-fifth of the estate over a five-year cycle, verifying asset status. Losses arise from assets no longer maintained due to changes in site activity, cost of repair, or evolving business requirements.