Question to the Department for Transport:
To ask the Secretary of State for Transport, how many publicly-funded charging points for electric vehicles have been delivered in each of the last 10 years; and how many such points are planned for delivery in 2015.
The number of publicly-funded chargepoints for electric vehicles that have been delivered in each of the last 10 years, including those for domestic use and those that are publicly accessible, is provided below. The first Government funding for chargepoints was in 2010/11 under the Coalition Government. Chargepoint installations in 2015/16 will depend on demand for domestic chargepoints and the detail of new infrastructure schemes to be announced later this year.
| 2010/11 | 2011/12 | 2012/13 | 2013/14 | 2014/15 |
| 579 | 1,401 | 3,644 | 9,520 | 42,423 |
This question was inadvertently grouped with 2324.