Channel Tunnel Railway Line: Electric Cables

(asked on 21st May 2019) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what recent representations the UK Government has made to the Channel Tunnel Intergovernmental Commission on regulatory approval for the installation of cabling for the Eleclink electricity interconnector between the UK and France.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 23rd May 2019

The UK Government is represented on both the Channel Tunnel Intergovernmental Commission (IGC) and the Channel Tunnel Safety Authority (CTSA). These groups meet several times each year and continue to work with Eleclink and Eurotunnel to progress consideration of this issue, following the suspension of consent for the project on safety grounds in October 2017.

In the light of the UK Government’s active role in relation to both the IGC and CTSA, the Government has not made separate representations to the IGC on the ElecLink project.