Question to the Department for Transport:
To ask the Secretary of State for Transport, what role he played in Riveroak Strategic Partners' application for a Development Consent Order on the site of Manston Airport; and what the (a) process and (b) timeframe is for his granting of consent after the Planning Inspectorate’s examination has concluded.
The Secretary of State for Transport has played no role in RiverOak Strategic Partners Ltd application for a Development Consent Order on the site of Manston airport.
The Examination of this application concluded on 9th July 2019. The Examining Authority now have three months to write their report and make a recommendation to the Secretary of State. The Secretary of State will then have three months in which to issue a decision.