Question to the Department for Transport:
To ask the Secretary of State for Transport, pursuant to the Answer of 1 October 2019 to Question 291482, what the length of time was between the submission of a strategic outline business case by the relevant sub-national transport body and the communication of an initial assessment of the proposed scheme by his Department for the most recent scheme costing over £100 million for which his Department provided such an assessment.
All Strategic Outline Business Cases which were submitted to the Department on 31st July have gone through a robust assessment process over the summer. This followed guidance made available on gov.uk.
The Department has been in contact with Sub-National Transport Bodies (STBs), including Transport East, to discuss the outcomes of the assessment process for all regions’ Strategic Outline Business Cases, including that for the provision of a North Ipswich bypass. Formal advice on the scheme will be sent to Suffolk County Council shortly.