Prisons: Procurement

(asked on 9th October 2026) - View Source

Question to the Ministry of Justice:

To ask the Secretary of State for Justice, pursuant to the Answer of 8 September 2026 to Question 23403 on Prisons: Procurement, what change in reporting approach by the National Infrastructure and Service Transformation Authority has resulted in a £1.28 billion saving in 2025/26.


Answered by
Catherine McKinnell Portrait
Catherine McKinnell
Minister of State (Ministry of Justice)
This question was answered on 21st October 2026

As set out in the annual report, the change in reporting approach relates to all costs being reported in 2024/25 base prices in line with NISTA requirements. This is a change from previous years where costs were reported in nominal prices.