M62

(asked on 9th March 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what the (a) start date and (b) cost is of the road schemes at M62 junctions 20 to 25 announced in the Autumn Statement 2014.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 14th March 2016

The Road Investment Strategy stated that work will start late in Roads Period 1, and the Highways England Delivery Plan states that the scheme will be in construction by March 2020.

The expected cost is £100-250m.