Question to the Ministry of Defence:

To ask the Secretary of State for Defence, with reference to the National Infrastructure and Service Transformation Authority Major Projects Annual Report 2025 to 2026, Tables, Mechanised Infantry Programme, what elements have been cut from the programme as part of the £1858.38 million funding removal and budget reprioritisation.


Answered by
Luke Pollard Portrait
Luke Pollard
Minister of State (Ministry of Defence)
This question was answered on 14th October 2026

As part of reprioritisation within the Military Strategic Headquarters, the Armoured Mortar, Repair and Recovery and Mounted Close Combat Overwatch capabilities of the Mechanised Infantry Vehicle programme are no longer being pursued.

The Army is considering how the underlying capability requirements will be addressed.