A14: Trees

(asked on 9th October 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the answer of 16 July 2026, to question 18240 on A14: Trees, what was the outcome of National Highways September 2026 survey on survival rates of replanted saplings.


Answered by
Justin Madders Portrait
Justin Madders
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 14th October 2026

As part of the trial replanting programme along the A14 roadside earlier this year, National Highways commissioned an interim survey of the replanted trees to assess survival rates. The survey was undertaken in late September 2026, and National Highways expects to receive the results by the end of October 2026. National Highways intends to undertake a further survey in the spring or summer of 2027 to assess longer-term establishment and survival rates of the replanted trees.