River Parrett: Flood Control

(asked on 22nd November 2023) - View Source

Question to the Department for Environment, Food and Rural Affairs:

To ask the Secretary of State for Environment, Food and Rural Affairs, what progress has been made on the construction of the River Parrett tidal barrier.


Answered by
Robbie Moore Portrait
Robbie Moore
Parliamentary Under-Secretary (Department for Environment, Food and Rural Affairs)
This question was answered on 1st December 2023

The Environment Agency has made significant progress with the Bridgwater Tidal Barrier scheme. The detailed design for the barrier and downstream banks is nearly complete. Environment Agency contractors are on site carrying out enabling works (constructing site compounds and access tracks and undertaking vegetation clearance). This will allow the construction of the bypass channel, barrier structure, control building and downstream banks over the next four years.

The Bridgwater Tidal Barrier is a flagship scheme delivering protection to 12,800 properties, along with £2 billion benefits for the local area. The scheme is expected to achieve £7.50 of benefits for every £1 spent.

Like many other major capital schemes, the Bridgwater Tidal Barrier project has seen cost increases due to inflationary pressures in construction, not least on concrete, steel, energy and labour costs, all of which are major elements of the scheme’s cost. The project is exploring options for funding as well as for efficiencies and savings to ensure that an operational barrier can be delivered as planned by early 2027. Identifying the optimum construction sequence will also enable us to achieve best value.