Question to the Ministry of Defence:
To ask the Secretary of State for Defence, what the planned schedule is for the refit of Point-class vessels a) Hurst Point, b) Hartland Point and c) Anvil Point under the Strategic Sealift Interim contract.
All 4 Point-class vessels are scheduled an extensive refit under the Strategic Sealift Interim contract. The planned schedule for RoRo refits are phased to maintain the strategic sealift capability required to support Defence operations. Timings remain subject to operational requirements, shipyard availability and the condition of each vessel when work begins.
Hurst Point is scheduled to dry dock in Q3 2027.
Hartland Point dry docked this year, 2026 – in Q3.
Anvil Point is scheduled to dry dock in Q2 2027.
Eddystone dry docked this year, 2026 – in Q2.