A1 (M): Repairs and Maintenance

(asked on 17th May 2022) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, when the southbound carriageway of the A1 between Newark and Grantham is schedule to be resurfaced; and if he will make a statement.


Answered by
Trudy Harrison Portrait
Trudy Harrison
This question was answered on 23rd May 2022

The southbound carriageway from Newark to Gonerby Moor is due to be resurfaced in late 2023/24, National Highways are currently developing a programme to resurface the remaining sections once this work has been completed. In recent inspections, National Highways identified a need for a series of patching works between Newark and Grantham and an emergency scheme is due to start in this area in the coming weeks.