Roads: Construction

(asked on 27th October 2026) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to the Answer of 16 October 2026 to Question 32938 on Roads: Construction, what value for money category was assigned to each of the four cancelled schemes in the most recent assessment undertaken prior to their cancellation.


Answered by
Justin Madders Portrait
Justin Madders
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 2nd November 2026

Before cancellation, each scheme had the following value for money category:

  • A303 Amesbury to Berwick Down – Low
  • A1 Morpeth to Ellingham – Poor
  • A12 Chelmsford to A120 widening – Poor
  • A47 Wansford to Sutton dualling - Medium/Low