Sheffield Supertram

(asked on 7th June 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what recent discussions he has had with Network Rail on delays to the Sheffield to Rotherham tram-train scheme.


Answered by
Andrew Jones Portrait
Andrew Jones
This question was answered on 14th June 2016

The Department for Transport and South Yorkshire Passenger Transport Executive, the joint funders of the tram train pilot project, have been advised that Network Rail has initiated a review of the current programme of works needed to adapt their infrastructure to operate the tram train vehicles between Meadowhall South and Rotherham Parkgate.

The Department understands that Network Rail has encountered significant issues with the approval of new bespoke electrification equipment needed to operate the tram train vehicles. The joint funders are clearly disappointed by this further delay.

The current programme showed delivery of these works by early spring 2017, however until the outcome of the Network Rail review is known, no further details can be provided.