East West Rail Line

(asked on 24th March 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, if she will make an assessment of the potential impact of East West Rail on Thameslink services (a) from London to Bedford, (b) from Bedford to London, (c) northbound on the East Coast Main Line and (d) southbound on the East Coast Main Line.


Answered by
Simon Lightwood Portrait
Simon Lightwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 1st April 2025

EWR Co’s proposals to use six tracking north of Bedford have been designed to mitigate impact on Thameslink services from Bedford to London. EWR trains will provide an interchange at Tempsford with East Coast Main Line services but will not run on the East Coast Main Line. There may be a slightly additional dwell time on some East Coast Main Line Thameslink services to accommodate the new stop at Tempsford.