Railways: North West

(asked on 26th June 2015) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, pursuant to his oral statement of 25 June 2015, Official Report, column 1067-8, on Network Rail, what effect changes to Network Rail's programme will have on upgrading of stock on and electrification of the lines between (a) Liverpool and Manchester and (b) Liverpool and Wigan.


Answered by
 Portrait
Claire Perry
This question was answered on 1st July 2015

The pause on Transpennine Electrification east of Stalybridge will have no effect on the plans to upgrade stock and the electrification of the lines between (a) Liverpool and Manchester and (b) Liverpool and Wigan, as those lines are now electrified.