High Speed 2 Line

(asked on 7th April 2025) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what her Department's original budget for HS2 Phase 2 was; how much her Department has spent since that project started; and what the estimated final cost is in (a) real and (b) current terms.


Answered by
Lilian Greenwood Portrait
Lilian Greenwood
Parliamentary Under-Secretary (Department for Transport)
This question was answered on 28th April 2025

The original funding envelopes (in 2015 prices) for Phase 2a was £3.72bn and £24.8bn for Phase 2b. Spend on the HS2 project can be found in the latest Parliamentary Report here , which is updated and published at regular intervals. The project currently reports estimated final costs in 2019 prices.