Railways: Wales

(asked on 20th May 2021) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, how much funding has been invested in the rail network in Wales in each of the last three years for which figures are available.


Answered by
Chris Heaton-Harris Portrait
Chris Heaton-Harris
Secretary of State for Northern Ireland
This question was answered on 26th May 2021

During this financial year (2021/2022), the third year of the current Network Rail Control Period (which runs from 2019 to 2024), planned spend on renewals in Wales is £226 million.

The past expenditure on renewals in Wales by year during this Control Period was £223 million in 2020/2021 and £185 million in 2019/2020.

While figures for expenditure on enhancements as a separate line item are not easily available given the nature of Network Rail funding and the different sources of funding for projects that are termed as ‘enhancements’, there was from FY18/19 to FY20/21 an estimated £143m invested in enhancements in Wales, predominantly in FY20/21.