Question to the Ministry of Housing, Communities and Local Government:
To ask the Secretary of State for Housing, Communities and Local Government, how many building control applications were received by the Building Safety Regulator (a) within and (b) after the statutory timeframe of 12 weeks in each month between October 2023 and April 2025.
The Department and the Building Safety Regulator recognise the value to the sector in providing performance data. From this quarter, the BSR will be publishing quarterly data demonstrating the volumes of applications received, recorded outcomes and decision times for determination.
Table 1 shows:
Table 2 shows:
Table 1 Approval Within 8 weeks SLA
Year / Month | No | Yes | Total Approvals |
2023 | 28 | 3 | 31 |
October | 6 | 0 | 6 |
November | 8 | 1 | 9 |
December | 14 | 2 | 16 |
2024 | 301 | 49 | 350 |
January | 23 | 5 | 28 |
February | 30 | 8 | 38 |
March | 35 | 6 | 41 |
April | 22 | 5 | 27 |
May | 34 | 4 | 38 |
June | 30 | 3 | 33 |
July | 30 | 6 | 36 |
August | 32 | 5 | 37 |
September | 30 | 5 | 35 |
October | 14 | 2 | 16 |
November | 10 | 0 | 10 |
December | 11 | 0 | 11 |
2025 | 8 | 0 | 8 |
January | 6 | 0 | 6 |
February | 2 | 0 | 2 |
March | 0 | 0 | 0 |
April | 0 | 0 | 0 |
Total | 337 | 52 | 389 |
Table 2- Approval within 12 weeks SLA
Year / Month | No | Yes | Total approvals |
2023 | 0 | 0 | 0 |
October | 0 | 0 | 0 |
November | 0 | 0 | 0 |
December | 0 | 0 | 0 |
2024 | 14 | 1 | 15 |
January | 1 | 0 | 1 |
February | 0 | 0 | 0 |
March | 0 | 0 | 0 |
April | 1 | 0 | 1 |
May | 7 | 0 | 7 |
June | 3 | 1 | 4 |
July | 0 | 0 | 0 |
August | 2 | 0 | 2 |
September | 0 | 0 | 0 |
October | 0 | 0 | 0 |
November | 0 | 0 | 0 |
December | 0 | 0 | 0 |
2025 | 0 | 1 | 3 |
January | 0 | 1 | 1 |
February | 0 | 0 | 2 |
March | 0 | 0 | 0 |
April | 0 | 0 | 0 |
Total | 14 | 2 | 18 |