To ask the Secretary of State for Transport, what assessment the Government has made of the likelihood of judicial review delaying the Heathrow Airport construction timetable.


Answered by
John Hayes Portrait
John Hayes
This question was answered on 24th November 2016

A third runway at Heathrow is expected to become operational by around 2026 subject to the Government’s consultation on a draft National Policy Statement and the planning process. We are confident that our process for decision-making is robust and will strongly defend any challenges with a view to maintaining this timetable.