Railways: Dawlish

(asked on 28th November 2016) - View Source

Question to the Department for Transport:

To ask the Secretary of State for Transport, what proportion of the £50 million investment in rail resilience projects referred to in paragraph 3.25 of the Autumn Statement 2016 is intended for the Dawlish Rail Resilience Project.


Answered by
Paul Maynard Portrait
Paul Maynard
Parliamentary Under-Secretary (Department for Work and Pensions)
This question was answered on 1st December 2016

The £10m of investment in Dawlish is 20% of the £50m rail resilience project investment announced in the Autumn Statement 2016. This funding will allow Network Rail’s development work to continue on the three highest priority Devon coastal sites identified in the geo-technical study which Network Rail published on 17 November. This work will include the development of an application for the necessary planning consents for the work on the cliffs along the coast to the immediate north-east of Teignmouth.